Major engineering work over Christmas has successfully delivered a £19m investment – including a new road bridge deck over the track at Camden – in just nine days. Trains between London St Pancras and Harpenden have resumed following the closure, which saw the 160-year-old Agar Grove structure in London completely removed and replaced to improve […]
↧